Most pages that answer this question are permit-software ads with fee guesses that don't match what the cities publish. This guide uses the cities' own documents: Plano's 2024 Residential Code ordinance, Frisco's fee schedule effective October 1, 2026 and its January 2026 summary of local amendments, and McKinney's 2024 code ordinance and Building Inspections pages. Where a city document could not be found or opened, we say so instead of guessing.
Do you need a permit for a deck in Plano, Frisco or McKinney? (the short version)
Plan on a permit in all three cities for any deck that is attached to the house, larger than 200 square feet or more than 30 inches off the ground. Only Plano publishes a clear small-deck exemption; for Frisco and McKinney we could not confirm the exemption text, so ask the city before you skip a permit.
| Question | Plano | Frisco | McKinney |
|---|---|---|---|
| Code in force | 2024 IRC with local amendments (Ordinance No. 2025-6-15) | 2024 IRC with amendments, effective March 1, 2026 | 2024 codes, adopted October 1, 2025 |
| Small-deck exemption | Yes: 200 sq ft or less, 30 in or less above grade, not attached, not serving the exit door (all four) | Could not be confirmed; ask the city | No city-written deck exemption; ask the city |
| Deck fee line | None named; two lines could apply | $75 plus $0.59 per sq ft, $550 maximum | No current fee found; ask the city |
| Published review time | 5 working days for residential comments | "As quickly as possible" | None published |
| How inspections are booked | eTRAKiT, SelecTXT or 972-941-7140 | eTRAKiT, by 7 a.m. on the day | Citizen Self-Service (CSS), requested by the general contractor |
| Who must register | Contractors ($100 a year for a general contractor); homeowners working on their own home do not | All contractors, before the permit is issued | Licensed trades; a general contractor needs no registration |
| Penalty for no permit | Fine for each offense; each day is a separate offense | Double permit fee | Misdemeanor, up to $500 (up to $2,000 for fire safety, zoning or public health matters); each day is separate |
One warning before you search: results for this question sometimes show a deck page from the City of Plano, Illinois. Those are not the Texas rules. The Texas city's documents come from plano.gov.
City of Plano TX deck building permit requirements (residential deck permit, official rules)
Plano's 2024 Residential Code exempts a deck only when it passes all four tests in its exemption list; fail one and you need a building permit. The city adopted the 2024 International Residential Code (IRC) with local amendments in Ordinance No. 2025-6-15.
Under section R105.2 (Building, item 10), a deck is exempt from a permit only if it is:
- 200 square feet or less in area.
- No more than 30 inches above grade at any point. One low corner doesn't count; the highest point does.
- Not attached to a dwelling or townhouse.
- Not serving the exit door required by section R311.4.
Put the other way: any attached deck, any deck over 200 square feet, any deck more than 30 inches up at any point, or a deck that serves the required exit door needs a permit in Plano.
What "serves the exit door" means in practice
If the deck is the landing outside your back door and its stairs are how you get down to the yard, it likely serves the exit door, so plan on a permit even if the deck is small and low. Landing and step rules at that door are covered in our guide to deck stair code.
Attached means a permit
A deck bolted to the house fails the third test no matter how small it is. If you are weighing the two designs, see attached vs freestanding decks.
Don't mix up the deck rule and the shed rule
The same exemption list lets one-story detached accessory structures up to 120 square feet go without a permit. That line is for sheds and similar buildings, not decks. A deck is judged by its own four tests.
A worked example
A 12 x 16 foot deck is 192 square feet, so it passes Plano's size test. A 14 x 16 foot deck is 224 square feet and needs a permit on size alone. Passing the size test is not enough, though: the 12 x 16 deck is exempt only if it is also freestanding, no more than 30 inches high at every point and not serving the exit door.
Adding a roof changes the picture. Plano's patio cover checklist reviews an attached cover as an addition to the house and says it can't be anchored to brick or siding veneer. If you are planning a deck in the city, see our page for the deck builder serving Plano.
Does a deck need a permit in Frisco?
Assume yes: Frisco says a permit is required for any residential or miscellaneous structure that is erected, constructed, enlarged, altered, repaired, moved or improved, and its fee schedule has a line just for decks.
Frisco's permit FAQ also says all accessory structures (it lists patio covers, storage buildings, gazebos, arbors and detached garages) need a building permit before construction and must meet setbacks and zoning.
Frisco has been on the 2024 IRC, with amendments, since March 1, 2026, under Ordinance 2026-01-10. Its January 2026 summary of those local amendments mentions only one change to the permit-exempt list (retaining walls up to 24 inches) and doesn't mention decks. We could not open the full amendment text, so we could not confirm whether Frisco keeps a small-deck exemption. Ask Frisco Building Inspections before you build any deck without a permit.
Frisco reviews residential additions and alterations electronically, and you can reach Plans and Permits at 972-292-5301. For local projects, see our page on Frisco covered patios and decks.
Does a deck need a permit in McKinney?
McKinney moved to the 2024 codes on October 1, 2025 and didn't write its own deck exemption, so check with Building Inspections before you skip the permit.
McKinney's 2024 IRC ordinance adopts the North Central Texas Council of Governments (NCTCOG) March 2025 regional amendments. The city's own change to the "work exempt from permit" section rewrites only paragraph 1, the one for one-story detached accessory structures up to 120 square feet. It doesn't touch the deck item. That means McKinney's small-deck rule comes from the 2024 IRC and the regional amendments, and we could not open either text to confirm it.
McKinney's "Home Repairs and Permit Information" page sends accessory structures to its Residential Alteration / Addition Guide. You apply in the Citizen Self-Service (CSS) portal by entering "Residential Alteration", and the city's Development Navigation Assistant (DNA) gives a step-by-step guide for your project. Decks are not on the page's list of work that doesn't need a permit; that list covers finish work and minor electrical, gas, mechanical and plumbing work.
If your home is in a historic area, ask about that too: McKinney's 2021 residential addition checklist included "Historic Approval (if applicable)". For local projects, see our deck builder in McKinney page.
What you submit: drawings, site plan and documents
Expect to submit a site plan showing the deck and its distance to every property line, plus scaled framing and footing drawings.
Plano. You hand in an application packet with a plan review deposit, 2 copies of scaled and dimensioned plans, and supporting documents. The city checks the packet for completeness at submission, and if the minimum documents for the scope aren't there, the submittal is rejected. Plano's checklist for accessory buildings shows the level of detail it expects: 2 sets of drawings, a site plan at 1"=20', scaled and dimensioned plans showing framing (including lumber spans), foundations and electrical, and exterior elevations. Expect similar drawings for a deck.
Frisco. Frisco's residential alteration form (Form 4038) has no deck section, so ask which application type to use. Its closest section, for arbors, patio covers, gazebos, carports, sunrooms and similar structures, shows what Frisco wants to see: a plot plan (survey) marked with the structure and its distance to all property lines; framing drawings with dimensions, front and side elevations, a material list and post and beam sizes; bracket types, bolt size and length and what it attaches to, if it is attached to the house; and a footer detail sheet showing how posts are anchored, the hole depth, concrete and rebar.
McKinney. McKinney's 2021 addition submittal list (the newest one we could open) asks for a site plan with distances to each property line and easements.
None of the documents we opened gives a deck setback from the property line. The site plan has to show those distances, so ask the city what setbacks your zoning sets.
| Item | Plano | Frisco | McKinney |
|---|---|---|---|
| Site plan | Yes, at 1"=20' (accessory building checklist) | Plot plan (survey) with distances to all property lines (Form 4038) | Distances to each property line and easements (2021 form) |
| Framing drawings | Scaled, dimensioned, with lumber spans (accessory checklist) | Dimensions, elevations, material list, post and beam sizes | Not published |
| Footing detail | Foundations shown (accessory checklist) | Footer detail sheet: post anchors, hole depth, concrete, rebar | Not published |
| Attachment detail | Covers can't anchor to brick or siding veneer (patio cover checklist) | Brackets, bolt size and length, what it attaches to | Not published |
| Electrical | Shown on plans; covers must show fans, switches and outlets | Not listed in that section | Not published |
| Engineer seal | Code says regulated footings must be sealed; ask how it applies | Required for aluminum, steel or vinyl structures; ask about wood decks | Not published |
| HOA note | Contact your HOA about deed restrictions | "Some subdivisions require HOA approval" | City encourages HOA approval before submittal (2021 form) |
How much does a deck permit cost in Plano, Frisco and McKinney?
Frisco is the only one of the three that prices decks directly: $75 plus $0.59 per square foot of gross area, capped at $550, on the schedule effective October 1, 2026. Plano has no deck line, and we could not find a current McKinney fee.
Frisco
The Deck line sits under "Outdoor Improvements" and uses the same formula as patio covers and arbors. The same page lists a $50 non-refundable application fee in the alterations block just above it; it isn't clear whether that applies to decks, so ask.
Plano
Plano's fee schedule (Ordinance 2025-11-4) doesn't name decks, and it doesn't say which line a deck uses. Two lines could apply:
- Residential (addition, alteration, backyard cottage): $40 minimum fee, building permit $0.48 per square foot, plus $45 plan review, plus electrical at $0.01 per square foot ($45 minimum) if there is wiring.
- Accessory structure (under 400 sq ft): $75.
A plan review deposit of 65% of the building permit fee is due up front and is non-refundable. If you withdraw a permit before any work starts, fees over $100 can be refunded at 80% (not counting plan review deposits), and fees under $100 are non-refundable.
McKinney
We could not open a current McKinney building permit fee schedule, so ask the city for the fee on your deck.
| Example | Fee | How it was calculated |
|---|---|---|
| Frisco, 200 sq ft deck | $193 | $75 + (200 x $0.59 = $118) |
| Frisco, 300 sq ft deck | $252 | $75 + (300 x $0.59 = $177) |
| Frisco, 500 sq ft deck | $370 | $75 + (500 x $0.59 = $295) |
| Frisco, about 805 sq ft or more | $550 | Cap reached: ($550 - $75) / $0.59 = 805.1 sq ft |
| Frisco, 300 sq ft deck started without a permit | $504 | Double permit fee: 2 x $252 |
| Plano, 300 sq ft deck, if billed at the residential addition rate | $189, plus electrical ($45 minimum) if wired | 300 x $0.48 = $144, + $45 plan review; Plano's schedule has no deck line |
| Plano, if billed as an accessory structure under 400 sq ft | $75 | Flat fee on the schedule; Plano's schedule has no deck line |
Frisco examples are calculated from Frisco's fee schedule effective October 1, 2026 and don't include the possible $50 application fee or any re-inspection fees. The Plano examples are calculated from Plano's fee schedule; the city decides which line applies.
Either way, the permit is a small slice of the total. For the full budget, see what a deck costs in Plano.
How long does deck permit review take?
Plano's published goal is 5 working days for residential plan review comments; Frisco and McKinney don't publish a residential review time. Frisco says applications "are reviewed as quickly as possible."
The fastest way to lose time in Plano is an incomplete packet, because it is rejected at submission. If the reviewer can't approve the plans as submitted, you get an email listing corrections. Changes must be clouded and marked with a delta, and you resubmit only the pages affected.
For the full schedule, see how long a deck takes, permit to finish.
Deck inspections: which ones, and how to schedule them
Each city gives you its inspection steps with the permit, and you or your builder must book each one before the work is covered up. None of the city pages we opened lists deck inspection stages by name, so go by the list that comes with your permit.
Plano
The permit comes with the required inspections in order, plus the inspector's name and phone number. Plano inspects at your request as work progresses, booked through eTRAKiT, the SelecTXT text line or 972-941-7140.
One set of stamped approved plans goes back to you and must stay on the job site for the inspector. Plano can charge a re-inspection fee if the work isn't ready, the address or permit card isn't posted, the approved plans aren't on site, the work is locked or unavailable, or the site is red-tagged twice for the same item. Re-inspections cost $75 the first time, $100 the second, $125 the third and $150 each time after that.
Frisco
Field documents must be submitted before you schedule. Online requests through eTRAKiT need a valid registration, and the cut-off is 7 a.m. on the day of the inspection; inspections are assigned at 7 a.m. Cancellations must be made before 8 a.m.
The residential re-inspection fee is $50 on the schedule effective October 1, 2026 (the city's February 2026 inspection checklist listed $30). Inspections are suspended once $120 or more in unpaid re-inspection fees has built up.
McKinney
McKinney says inspections on permitted work "should be requested by the general contractor," scheduled through CSS. To cancel, call 469-617-4800 before 9 a.m.; after that, call the inspector. If rain makes the site too wet and the inspection wasn't cancelled, expect a red tag and a $50 re-inspection fee.
How long a permit stays valid
Plano allows 180 days (6 months) to begin work, and work must keep going once started to avoid expiration. Its accessory building sheet adds that a permit inactive for 180 days is abandoned and can be renewed for another 180 days, for a fee. McKinney's 2021 application says a permit becomes invalid if work doesn't start within 180 days of issue or stops for 180 days, and that all permits require a final inspection. We did not find Frisco's expiration period.
Do deck footings need an engineer's seal in Plano or Frisco?
Possibly. Plano's amended code says every footing it regulates must be designed and sealed by a Texas-registered engineer, and Frisco requires engineer-sealed structural design for homes, so ask before you price the job.
Plano. The amended R401.2 says every foundation or footing regulated by the code "shall be designed and sealed by a Texas-registered engineer." It doesn't name decks, and no Plano document we found says how the rule is applied to deck piers. Ask Building Inspections or your builder whether your deck's footings need a seal.
Frisco. Frisco's local amendments require all residential foundations, framing and overall dwelling structural design to be prepared, signed and sealed by a Texas-licensed Professional Engineer who is also registered with Frisco and carries at least $1 million in professional liability insurance. That wording is about the house's structure; it doesn't say deck footings need an engineer, so ask whether your deck plans need a seal. Separately, Form 4038 asks for engineering when a patio cover or similar structure is aluminum, steel or vinyl.
McKinney. We found no McKinney rule on engineered deck footings. Ask when you apply.
Plano's code climate table lists a frost line depth of 6 inches and termite risk as "Very Heavy," which is worth knowing when you choose post materials and footing depth. We found no published engineering cost, so get it in writing from your builder or engineer.
Who can pull the permit: contractor registration and homeowner permits
In Plano a homeowner can pull a permit for work on their own home without registering, but a contractor must be registered with the city, at $100 a year for a general contractor. At approval, the general contractor is required to register with the City of Plano.
Plano also holds contractors to their inspections. Its accessory building sheet says missing required inspections "can result in the contractor registration being put on hold," and the code allows a registration to be suspended for failing to finalize permits with the required inspections.
Frisco. Every contractor who works in Frisco must register with Building Inspections before the permit is issued. Registration takes an online application, insurance information, any master's licenses and fees, and gives the contractor an "R-Number" that expires when their general liability insurance does. General contractors are on the list of trades that must register. We did not find whether a Frisco homeowner can pull their own permit.
McKinney. Licensed contractors must register before a permit is issued, but for a general contractor "Contractor registration is not required": there is no fee or form, and the general contractor just opens a CSS account. A Signature Verification Form is required for each project. We did not find whether a McKinney homeowner can pull their own permit.
A simple check: ask your builder for their Plano or Frisco registration, then look it up on eTRAKiT, which Frisco uses to check contractor registration.
HOA approval is a separate step
A city permit doesn't replace HOA approval, and all three cities point you to your HOA, so get the architectural committee's written OK first. Plano's accessory building and patio cover checklists tell you to contact your HOA, Frisco's Form 4038 notes that some subdivisions require HOA approval, and McKinney's 2021 application "encourages you to have approval from your HOA prior to submittal."
The city checks code and zoning; the HOA checks its own deed restrictions, such as where a deck can go and what it can look like. One approval doesn't count for the other.
What happens if you build a deck without a permit?
You risk fines that count every day as a new offense, a doubled permit fee in Frisco, and a question you'll have to answer when you sell.
- Plano: anyone violating the Residential Code faces a fine under Section 1-4(a) of the City Code for each offense, and every day a violation continues is a separate offense. We could not find the dollar amount in Section 1-4(a).
- Frisco: non-emergency work started without a permit is charged a double permit fee. For a 300 square foot deck, that is 2 x $252 = $504 on the current schedule, before any re-inspection fees (calculated).
- McKinney: under McKinney's 2024 code ordinance, a violation is a misdemeanor with a fine of up to $500, or up to $2,000 for violations relating to fire safety, zoning, or public health and sanitation. Each day is a separate violation.
- Selling the house: the Texas Seller's Disclosure Notice (Property Code section 5.008) asks whether the seller knows of "room additions, structural modifications, or other alterations or repairs made without necessary permits or not in compliance with building codes in effect at that time." A seller who knows a deck was built without a required permit must disclose it on that form.
Before you build: a checklist
- In Plano, check the deck against all four exemption tests: size, height at every point, attachment and the exit door.
- In Frisco or McKinney, ask Building Inspections whether your deck is exempt before you skip a permit.
- Get HOA approval in writing.
- Have a site plan that shows the deck's distance to every property line, and ask the city for your setbacks.
- Ask whether your footings or framing need an engineer's seal.
- Confirm who will pull the permit and that they are registered with the city where required.
- Keep the approved plans and permit card on site.
- Book every inspection on the list that comes with the permit, and get the final.